Writing 'rained all day' rarely explains what actually happened on site. A useful weather record connects the conditions to the work, time and practical response.
The aim is not to make a dramatic claim. It is to create a clear record that another person can understand later.
Record the weather as it changes
- Approximate start and finish times
- Changes in rain, wind, heat or cold
- Ground and access conditions at arrival
- A weather source or screenshot where useful
- The actual conditions observed on site
Identify the exact work affected
Do not describe the whole project as delayed if only one activity stopped. Record the planned task, location, crew, plant or delivery affected and whether the work stopped, slowed or moved elsewhere.
Exterior membrane installation on the east elevation stopped at 10:05 am due to wind-driven rain. Two installers moved to internal preparation work in Units 2 and 3.
Separate lost time from changed work
A weather event does not always mean the whole crew lost the same number of hours. Note each crew or activity, what was planned, what actually happened and the time affected.
Photograph the condition and its effect
- Standing water or saturated ground
- Unsafe or blocked access
- The exposed work area
- Temporary protection
- Material condition
- The activity that could not proceed
Record the response
- Moved the crew to another activity
- Installed or repaired temporary protection
- Pumped water or protected materials
- Contacted a supplier or subcontractor
- Rescheduled an inspection or delivery
- Checked the next suitable work window
Note the programme effect carefully
There is a difference between a task being interrupted and the project completion date changing. Record the immediate effect and update the programme impact when it is known rather than guessing.
Roof-sheet installation moved to the next suitable work window. Programme effect to be reviewed after confirming the roofing crew's availability.
Connect the record to project notices
- 1
Check the project documents
Use the actual contract or agreed procedure rather than a generic assumption.
- 2
Identify the notice requirement
Confirm the method, recipient and any relevant timing.
- 3
Send the notice separately
Reference the factual site record and supporting photographs.
- 4
Update the record
Add the known programme effect and next review date.
This is general record-keeping information, not legal or contractual advice.
Keep the record connected
Related guides and templates
Field guide
What to Record in a Daily Site Diary
A practical daily site diary guide for builders, subcontractors and tradies, with a free fillable template.
Read this resourceField guide
How to Take Useful Construction Site Photos
A simple before, during and after photo system that makes construction photos easier to understand and find.
Read this resourceFree template
Free Weather Delay Record Template
A two-page fillable record connecting observed weather with affected work, time, mitigation and follow-up.
Read this resourceQuestions or a better way to do it?
Open comments are not enabled yet. Send us a correction, question or site-tested suggestion and we will use it to improve the guide.